March 6, 2026
The U.S. Nuclear Regulatory Commission on Wednesday approved its first construction permit for a commercial nuclear reactor in eight years, one that will allow a Bill Gates-backed company to build a sodium-cooled reactor in western Wyoming.
TerraPower filed for the permit in 2024 and construction is now set to begin within weeks. Completion of the up to $4 billion plant is targeted for 2030, according to TerraPower. Microsoft co-founder Gates, who is eyeing nuclear generation as a power source for the electricity-hungry data centers behind artificial intelligence, is a founder of TerraPower and its primary investor.
. . .